PLAI

Decision

Saura Import v. Development Bank Of The Philippines

G.R. No. L-24968 · 1972-04-27 · MAKALINTAL, J. · LawPhil

SAURA IMPORT and EXPORT CO., INC., plaintiff-appellee, vs. DEVELOPMENT BANK OF THE PHILIPPINES, defendant-appellant. Mabanag, Eliger and Associates and Saura, Magno and Associates for plaintiff-appellee. Jesus A. Avanceña and Hilario G. Orsolino for defendant-appellant

MAKALINTAL, J.:

In Civil Case No. 55908 of the Court of First Instance of Manila, judgment was rendered on June 28, 1965 sentencing defendant Development Bank of the Philippines (DBP) to pay actual and consequential damages to plaintiff Saura Import and Export Co., Inc. in the amount of P383,343.68, plus interest at the legal rate from the date the complaint was filed and attorney's fees in the amount of P5,000.00. The present appeal is from that judgment. In July 1953 the plaintiff (hereinafter referred to as Saura, Inc.) applied to the Rehabilitation Finance Corporation (RFC), before its conversion into DBP, for an industrial loan of P500,000.00, to be used as follows: P250,000.00 for the construction of a factory building (for the manufacture of jute sacks); P240,900.00 to pay the balance of the purchase price of the jute mill machinery and equipment; and P9,100.00 as additional working capital.

Parenthetically, it may be mentioned that the jute mill machinery had already been purchased by Saura on the strength of a letter of credit extended by the Prudential Bank and Trust Co., and arrived in Davao City in July 1953; and that to secure its release without first paying the draft, Saura, Inc. executed a trust receipt in favor of the said bank. On January 7, 1954 RFC passed Resolution No. 145 approving the loan application for P500,000.00, to be secured by a first mortgage on the factory building to be constructed, the land site thereof, and the machinery and equipment to be installed. Among the other terms spelled out in the resolution were the following: 1.

That the proceeds of the loan shall be utilized exclusively for the following purposes: For construction of factory building P250,000.00 For payment of the balance of purchase price of machinery and equipment 240,900.00 For working capital 9,100.00