Universal Robina Corp. v. Laguna Lake Development Authority

Universal Robina Corp. (Corn Division) v. Laguna Lake Development Authority, G.R. No. 191427, May 30, 2011

G.R. No. 191427May 30, 2011Ponente: CARPIO MORALES, J.
  • Procedural (Remedial Law)
  • Political Law
  • environmental law
  • Laguna Lake Development Authority
  • wastewater effluent standards
  • daily penalties
  • exhaustion of administrative remedies
  • administrative due process
  • certiorari
  • self-serving evidence
  • DENR Administrative Orders
  • pollution

Read the full decision

I. Facts of the Case

Universal Robina Corp. manufactures animal feeds and operates a corn oil refinery plant in Bagong Ilog, Pasig City. The Laguna Lake Development Authority (LLDA) found that the plant's wastewater repeatedly failed government effluent standards and ordered it to pay accumulated daily penalties. Universal Robina contested the computation of the penalties and the LLDA's rejection of its operation reports, and questioned the fairness of the proceedings.

  1. March 14, 2000

    LLDA's Pollution Control Division analyzed the wastewater of Universal Robina's corn oil refinery plant. It found that the wastewater failed to comply with the standards in DENR Administrative Orders Nos. 34 and 35, series of 1990.

  2. May 30, 2000

    LLDA issued an Ex-Parte Order requiring Universal Robina to explain why no order for cessation of its operations should issue. The grounds were discharge of pollutive effluents into the Pasig River and operation without an LLDA clearance/permit.

  3. August 31, 2000

    After a phone-in complaint, LLDA conducted another analysis. It showed continued failure to meet effluent standards for TSS, BOD, Color and Oil/Grease.

  4. March 1, 2001

    Hearings on the pollution case began. Later compliance monitoring and inspections still showed the wastewater failing the DAO parameters.

  5. Early 2003

    Universal Robina notified LLDA of its plan to upgrade its wastewater treatment facility. The upgrade was completed only in 2007.

  6. May 9, 2007

    At Universal Robina's request, a re-sampling was conducted. It showed that the plant finally complied with government standards.

  7. June 19, 2007

    At a hearing, LLDA gave Universal Robina 15 days to submit valid documents proving its non-operating dates. Universal Robina failed to comply.

  8. August 24, 2007

    Universal Robina filed a Manifestation and Motion asking for a reduction of penalties. It attached unverified Daily Operation Reports and Certifications to show that penalties should cover only 560 days.

  9. January 21, 2008

    LLDA issued an Order to Pay PHP 1,247,000 in accumulated daily penalties. It covered 932 days (March 14, 2000 to November 3, 2003) and 448 days (March 15, 2006 to April 17, 2007), stated as a total of 1,247 days.

  10. Universal Robina moved for reconsideration, seeking to pay only P560,000. It argued that LLDA wrongly assumed daily operation, failed to exclude the 212 days of LLDA Laboratory rehabilitation (December 1, 2000 to June 30, 2001), and disregarded its Daily Operation Reports and Certifications.

  11. July 11, 2008

    LLDA denied reconsideration. It explained that its computation used six operating days per week, deducted the laboratory rehabilitation period and the two years and four months without inspection, and rejected the documents as self-serving. It stated the second period as 342 days, for a total of 1,274 days.

  12. Universal Robina filed a certiorari petition with the Court of Appeals, alleging grave abuse of discretion. It claimed it had no plain, speedy or adequate remedy, as an exception to exhaustion of administrative remedies.

  13. October 27, 2009

    The Court of Appeals affirmed both LLDA orders. It held they were supported by substantial evidence and in accord with DENR guidelines, that LLDA could disregard the unverified documents, and that the petition was premature for failure to appeal to the DENR Secretary or the Office of the President.

  14. February 23, 2010

    The Court of Appeals denied reconsideration. Universal Robina then filed a petition for review on certiorari before the Supreme Court.

II. Issues

1
Procedural (Remedial Law)

Whether or not petitioner's recourse to the Court of Appeals by certiorari was proper despite its failure to exhaust administrative remedies by appealing to the DENR Secretary.

2
Political Law

Whether or not petitioner was deprived of due process in the proceedings before the LLDA.

3
Procedural (Remedial Law)

Whether or not the LLDA correctly computed the accumulated daily penalties and validly disregarded petitioner's unverified Daily Operation Reports and Certifications.

III. Ruling

Issue 1Procedural (Remedial Law)

Whether or not petitioner's recourse to the Court of Appeals by certiorari was proper despite its failure to exhaust administrative remedies by appealing to the DENR Secretary.

No

Certiorari was not proper because petitioner could have appealed the LLDA orders to the DENR Secretary and did not. Its claim that an appeal would be futile was mere speculation.

How the Court reasoned

  1. Parties must first use all available remedies within the administrative system before going to court. This is the doctrine of exhaustion of administrative remedies.
  2. Under the implementing rules of R.A. 4850, LLDA orders may be appealed to the DENR Secretary.
  3. Petitioner skipped this appeal and went straight to the Court of Appeals by certiorari.
  4. Petitioner argued it had no plain, speedy or adequate remedy, but the DENR appeal was such a remedy.
  5. Its claim that the appeal would be futile was speculative and presumptuous, so no exception to exhaustion applied.
“Petitioner had thus available administrative remedy of appeal to the DENR Secretary.”

Rule applied

Doctrine of exhaustion of administrative remedies; Rule X, Section 2, 2004 Revised Rules, Regulations and Procedures Implementing Republic Act No. 4850

Issue 2Political Law

Whether or not petitioner was deprived of due process in the proceedings before the LLDA.

No

Petitioner was not denied due process. It was heard and had full opportunity to present evidence and seek reconsideration.

How the Court reasoned

  1. Due process in administrative proceedings does not require a full trial-type hearing. It requires only notice and a fair chance to be heard.
  2. LLDA issued show cause orders and held hearings, so petitioner was informed of the charges.
  3. Petitioner was allowed to present evidence, including its Manifestation and Motion with attached reports.
  4. It received notice of the Order to Pay and was able to move for reconsideration.
  5. These steps satisfied the minimum requirements of administrative due process.
“Due process, as a constitutional precept, does not always and in all situations require a trial-type proceeding.”

Rule applied

Administrative due process; Section 1, Article III of the Constitution

Issue 3Procedural (Remedial Law)

Whether or not the LLDA correctly computed the accumulated daily penalties and validly disregarded petitioner's unverified Daily Operation Reports and Certifications.

Yes

LLDA correctly computed the two violation periods and the daily penalties. It could treat petitioner's unverified reports and certifications as self-serving.

How the Court reasoned

  1. LLDA Resolution No. 33 imposes a daily penalty for each day of violation of effluent standards.
  2. LLDA reckoned two periods of violation, from the initial sampling to the request for re-sampling and then from the later re-sampling date to April 17, 2007. It excluded the long interval without monitoring and the laboratory rehabilitation period.
  3. LLDA used six operating days per week, which already gave petitioner some allowance for non-operating days.
  4. Petitioner's Daily Operation Reports and Certifications were unverified, and it failed to submit valid proof within the 15 days given.
  5. LLDA's own reports contradicted petitioner's documents, and petitioner never disputed those reports.
  6. Absent verification, LLDA could treat the documents as self-serving.
  7. Environmental protection is as urgent as private enterprise concerns, and petitioner's delay in upgrading its facility showed a lack of genuine concern.
“Absent such verification, the LLDA may not be faulted for treating such evidence to be purely self-serving.”

Rule applied

Article VI, Section 32 of LLDA Resolution No. 33, Series of 1996; substantial evidence rule in administrative proceedings

Doctrines

1

Due process in administrative proceedings does not always require a trial-type hearing. It is satisfied when the party is notified and given a fair opportunity to be heard and to seek reconsideration.

2

A party must exhaust available administrative remedies, such as an appeal to the DENR Secretary from LLDA orders, before resorting to judicial review. A bare claim of futility is not an exception.

3

Unverified documents submitted as evidence may be treated by an administrative agency as self-serving, especially when contradicted by the agency's own undisputed reports.

4

Protection of the environment is no less urgent than the concerns of private enterprise.

Final Disposition

WHEREFORE, the petition is DENIED. The Decision and Resolution of the Court of Appeals are AFFIRMED.

Notes

The LLDA orders stated inconsistent day counts: 1,247 days in the Order to Pay and 1,274 days in the order denying reconsideration (342 days for the second period). The Court upheld the computation and the P1,247,000 penalty.